Posted in Construction, Pictures on Feb 29th, 2008 1 Comment »
Since our house is a SIP house, it’s some extra work to put plugs and switches in the exterior walls. There will be times when it’s unavoidable, but we’re trying to minimize the situation both because it will be easier and we don’t want to pierce the envelop of the walls if we can avoid […]
Read Full Post »
Posted in Pictures, Plumbing on Feb 25th, 2008 5 Comments »
We’re well on our way on the next phase of house building - Drain, Waste, Vent plumbing. The last month or so, I’ve been doing a lot of thinking and planning and the last couple of weeks have been busy executing, modifying and adapting the plan.I’m happy to say that I’ve now finished all 3″ […]
Read Full Post »
We’ve been spending a bit of time walking around the house, looking at the bare, framed walls and imagining how out stuff will fit into it. Thinking about how we’ll be using the space. Considering if it’s all “right”.
We have come to the realization that the master isn’t quite right for our bed. Amber and […]
Read Full Post »
Posted in Announcements on Feb 5th, 2008 No Comments »
I just updated the mast image to better reflect the current state of the house - sided and roofed.
The new mast image was taken on 2/3/2008 at about 8:15 AM PST looking South.
Read Full Post »
I feel like the month of January was mostly a time for catching our breath and figuring out what’s next.
The structure is totally up (walls and roof). Most internal framing is done. The roof material is on and most of the siding, trim and fascia are done. External doors are hung, windows are in and […]
Read Full Post »